Why queue reform can only go so far in speeding up grid connections
Graeme Hutchison explains how phased, shared and smaller connections can help projects get moving despite equipment and skills shortages.

Managing Director of Grid Consultancy at Eclipse Power.

Could smaller, phased or shared connections help unblock the grid connection queue? Dr Graeme Hutchison, Managing Director of Grid Consultancy at Eclipse Power, explores.
The UK grid is constrained, and so too is the capacity to build it out. Essential equipment such as transformers, switchgear and high-voltage cables are scarce compared to the levels of demand for them, and the engineers required to install and energise them are in short supply too.
Over the long term, the best way to address this issue is to increase the supply of materials and people by building our manufacturing base, and training a new generation of grid engineers. But in the short-to-medium term, getting projects energised faster relies on making better use of existing resources, and that in turn depends on streamlining grid delivery models.
Connections reform is a partial solution
The move from ‘first come, first connected’ to a ‘first ready, first needed, first connected’ connections queue has been helpful. It’s reordered the queue to favour the supply and storage projects we need, while demoting speculative applications and those less ready to proceed. Similar proposals for demand-side reform should be equally useful in prioritising viable projects, if they go ahead.
But a change in the order of the projects that get the green light to proceed doesn’t fundamentally alter or expand the deliverable capacity of the system. According to the IEA’s research, transformer and cable lead times have risen by 75% and 100% respectively since 2021, while high voltage DC cable lead times can exceed five years.
In practice, this means that a developer could secure a strong queue position, only to find that they’re constrained by a lack of critical equipment or skilled resource. The issue, then, cannot simply be how developments queue, but how the sector uses its resources.
Reducing what the grid must supply
The first opportunity to use resources better is by reducing the grid capacity that each project seeks to what it genuinely needs. New developments can, in many cases, be created on microgrids or private networks that co-locate new generation with demand and storage. Aggregating developments that combine supply and demand users reduces the connection size they might need.
In my experience, co-location can have a significant impact: a development that might otherwise request several MVA may, through this approach, need much less. Every bit of capacity avoided at the connection releases upstream capacity, equipment and engineering resources.
Waiting for a bigger connection ultimately means using more resources. If multiple projects are connected independently rather than together through a shared, optimised connection, then resources and effort are unnecessarily multiplied. By designing connections shared by multiple users, network operators can use fewer resources and bring energisation dates forward.
Smarter can also mean phased. Not all developments need 100% capacity on day one, and a phased connection means developments can get up and running quicker. What’s more, it also produces a staggered need for substation equipment, cabling and skilled labour.
Putting existing assets to work
When it comes to equipment, delivery models can’t necessarily increase the supply of new assets. But independent distribution network operators (IDNOs) have greater flexibility than the incumbent operators in what they adopt onto their networks. A greater range of equipment, from more manufacturers and suppliers, can help circumvent queues for frequently specified equipment.
This flexibility can even help put suitable existing equipment back into service. Some IDNOs are now giving customers access to restored and remanufactured substation equipment, sourced from many places. This includes former temporary supplies, products from decommissioned sites, or simply stock that was produced but later not needed.
Provided safety, quality and lifecycle standards are as good as new equipment, this may transform energisation times for developments, with lead times reduced from several months to as little as a week, in some cases.
Optimising people power
Skills shortages are already well documented – particularly for higher-level engineering and technical roles – and training pipelines cannot expand quickly enough to meet immediate demand. However, engineers as a resource can be used in more or less efficient ways.
For example, an experienced IDNO can challenge the developers of larger schemes, questioning whether requested capacity, voltage level and connection points are optimised.
By interrogating assumptions behind the connection and its timeline, they can identify the project’s true requirements and stop developers wasting limited resources. And even when a project’s power assumptions are right, the full capacity may not be needed from day one – and instead could be phased, to get parts energised faster while waiting for upstream reinforcement.
This is particularly true of major projects connecting at extra-high voltage (EHV), where the skills and supply shortages are most acute. With the increased complexity of projects at this level, experienced partners can be essential to pre-empting and managing issues and stakeholders more effectively.
From IDNO to ITO and beyond
The IDNO model is well proven, with independents now connecting 80% of new homes in Great Britain. IDNOs have helped many developments get energised faster, and can make better use of the limited resources available in the sector. The natural next step is to apply what’s proven at the distribution level to the transmission network.
Ofgem is developing an independent transmission operator (ITO) licence as part of its demand-side connection reforms, alongside options for the self-build and ownership of high-voltage assets. Eclipse has previously applied for a transmission licence, and has long argued that allowing third parties to build, own and operate transmission connections would bring quicker, lower-cost connections and greater customer choice. What’s more, we believe introducing competition would create commercial incentives to invest in the supply-chain relationships and workforce capability that will help to deliver over the longer-term.
We cannot build our way out of scarcity overnight; supply is far from matching the current demand. Instead, we can and should find ways to better use what we have. The capacity, equipment and engineering talent available today can be deployed more effectively and efficiently, and the success of independent delivery models proves it. Extending that resource-efficient approach to transmission will help to turn scarce resources into energised projects.
The views and opinions expressed in this article are those of Dr Graeme Hutchison and do not necessarily reflect the official policy or position of Electrical Review. This content represents individual perspective and industry commentary.
Recommended Reading

Electrification alone won’t solve the heat challenge
Christophe Williams, founder of Naked Energy, asks whether we are putting too much of the heat challenge on the grid.

Are we overcomplicating the path to cheaper, cleaner energy?
Pulse Clean Energy’s Trevor Wills argues that the key to cheaper, cleaner power is deploying proven technologies at speed, not waiting for miracles.

Is grid connections reform finally fixing Britain’s queue problem?
Eclipse Power’s Laura Henry asks whether Britain’s grid queue overhaul offers real progress for developers facing tighter rules and uncertain dates.