Ofgem proposes £305m Sea Link allowance cut as harmonics issue remains unresolved
Ofgem has proposed cutting more than £305 million from NGET’s requested allowance for Sea Link, while raising concerns over a power quality issue.

In Brief
- Ofgem won’t give National Grid Electricity Transmission the full allowance it requested for its Sea Link project, reducing the amount by £305.5 million.
- The reduction largely relates to uncertain costs and risk allowances rather than concerns over the main converter and cable contracts.
- Despite the cost reduction, Ofgem is still concerned around an unresolved harmonics issue. Especially as harmonic studies found that even the largest filter solutions proposed by bidders were unlikely to meet applicable limits under all system conditions.
- NGET is carrying out further studies and expects additional work elsewhere on the transmission network will be needed to resolve the issue.
In Review
Ofgem has proposed cutting more than £305 million from National Grid Electricity Transmission’s requested allowance for Sea Link, while raising concerns over an unresolved power quality issue affecting the 2GW HVDC project.
By cutting the allowance, it means that NGET will receive £2.89155 billion in 2023/24 prices, rather than the £3.197 billion it was seeking.
So, why has the allowance been cut?
Well, it’s not because Ofgem believes Sea Link’s main construction contracts are overpriced. In fact, it’s quite the opposite. The regulator actually believes they’ve been competitively procured, and it has no material concerns over their cost.
Instead, much of the proposed reduction relates to uncertain expenditure and the amount of risk funding NGET requested upfront. Of course, Ofgem appreciates that there may be unexpected costs that crop up, but it’s not willing to write a blank cheque – and instead, NGET will have to recover the costs at a later stage if they materialise.
Harmonics require further work
Speaking on potential unexpected costs, Ofgem raised concerns over a significant technical issue concerning Sea Link’s ability to meet harmonic limits while operating at full capacity.
During detailed design and procurement, NGET found that even the largest harmonic-filter solutions proposed by bidders were unlikely to meet the required limits under all system conditions.
Further studies are now being carried out to establish what additional mitigation is needed. Ofgem says the measures currently proposed for Sea Link do not fully resolve the issue, and additional work elsewhere on the transmission network may also be required.
The final solution, location and cost have not yet been determined.
Ofgem has also made clear that reducing Sea Link’s output will not be an acceptable workaround.
The project must meet Grid Code requirements on voltage waveform quality while operating at its full 2GW capacity. If Sea Link has to be derated because of harmonic problems, Ofgem says NGET will not have delivered the required project outputs.
Pressure to accelerate delivery
Sea Link is designed to provide a new 2GW transmission connection between Suffolk and Kent using HVDC cables and converter stations. It was given a target delivery date of December 2031, although NGET says it’s been working towards a programme that could see it delivered a whole year early.
Ofgem cited the reasoning for bringing the project forward is because NESO estimated that it could cost consumers between £1.1bn and £1.4bn in additional constraint costs. The added cost of speeding up the works would therefore be more than recuperated. That’s why Ofgem is considering how further acceleration measures could be funded where NGET can show they would bring the project forward and deliver a clear consumer benefit.
Of course, that’s all dependent on planning. The Examining Authority submitted its recommendation to the Secretary of State in July, with a Development Consent Order decision expected by October 30, 2026.
Recommended Reading

National Grid announces £624m of network contracts across 78 suppliers
National Grid's latest contracts will support electricity network maintenance and upgrades over the next five years, with 69 SMEs included.

SSEN places first modular substation orders as 1GW rollout begins
SSEN Transmission has started placing firm orders for standardised substations, with 15 modules due to be ordered by the end of 2026.

National Grid secures approval for three 400kV substations
The substations will enable National Grid to uprate two existing transmission routes from 275kV to 400kV, adding 3 GW of network capability.
How will the North Sea Link interconnector impact the UK energy market?
The North Sea Link interconnector with Norway saw its first official use in June 2021, how will it impact the UK energy market?

Eastern Green Link 4 confirms £3bn supply chain contracts for UK subsea link
Eastern Green Link 4 has secured £3bn in major contracts, marking a key milestone for the 2GW subsea project linking Scottish and English grids.