UK Power Networks’ DSO unleashes 4GW of new capacity
UK Power Networks has unleashed 4GW of new network capacity, fast-tracking offers to more than 40 new energy projects in 2023.

Since launching the UK’s first independent Distribution System Operator, UK Power Networks has been working collaboratively with other networks to unleash 4GW of new network capacity, fast-tracking offers to more than 40 new energy projects in 2023.
As part of its work to unleash additional capacity, UK Power Networks has seen connection dates brought forward by more than a decade in some instances, enabling the rapid deployment of renewable energy and battery storage projects.
The initial phase of this initiative involves releasing 2.3GW across eight Grid Supply Points (GSPs) in 2023, with a further 1.7GW across four GSPs in early 2024.
By leveraging its Distributed Energy Resource Management (DERMS) platform, UK Power Networks is enabling new and emerging assets like large-scale battery storage to take advantage of existing system capacity. In fact, the company is allowing customers who accept the revised offers to connect as soon as they are ready to build.
This collaborative effort, spearheaded by UK Power Networks, is bringing about a paradigm shift in network connections, making it cheaper, easier, and faster for net-zero technologies to connect to the grid.
Matt White, Head of Network Strategy at UK Power Networks DSO, emphasised the significance of this achievement, stating, “Networks are working together and taking a whole-systems approach that is showing how we can deliver the capacity we need to reach Net Zero.
“Our DSO is demonstrating how the technology, people, and data that it is developing is making a tangible difference to our customers by fast-tracking gigawatts of capacity in our licence areas and beyond.
“We’re committed to making it cheaper, easier and faster for net zero technology to connect to the network, and we’re working closely with our fellow networks and the national transmission system to make it happen.”
Recommended Reading

National Grid to use flexible demand to manage voltage in 100 LV zones

Aegis starts construction of multi-energy commercial vehicle charging hub
Aegis expects the site to open in spring 2027, with 72 van bays and 30 truck bays at full build.

£190m motorway charging scheme may not protect grid capacity for electric HGVs
The scheme includes future eHGV demand when sizing motorway grid connections, but the allocation rules don't ring-fence any of that capacity.