Submarine cables for for grid strengthening project
In a contract worth 4.6m Euros, LofotKraft AS has once again selected Nexans to deliver and install 170 kV XLPE cables to upgrade the current systems in three fjords; Gimsøystraumen, Nappstraumen and Flakstadpollen to strengthen the power supply for residents throughout Lofoten, Norway. This will include upgrading the current grid capacity from 66 kV to 132 kV.
Lofotkraft AS will upgrade the submarine cable in all three fjords to extend longevity and solve issues related to inadequate transmission capacity. Nexans Norway will supply
the 170 kV XLPE cables with transition joints, end terminations and contingency repair joints.
The project begins this month, with supply of the submarine cable scheduled for spring 2017 at Nexans’ Halden plant in Norway.
We have just celebrated the 100th anniversary of Nexans Norway, which began in 1915 as Scandinavian Cable and Gummifabrik. Throughout this time, the Group has delivered more than 1500 submarine cable projects, which together contribute to over 50% of global transmission.
Tom Skattum, project manager at Nexans Norway said, “We are pleased to be working with Lofotkraft AS again as part of our 50 year long relationship. Upgrading this grid means we are not only increasing the capacity, but increasing the redundancy, ensuring energy security of the residents of Lofoten.”
Bjørn Harald Vian at Lofotkraft AS added : “The award is based on an overall assessment of the award criteria; price, project execution, quality and HSE. Furthermore, Nexans' experience and expertise in submarine cables were rated highly. In addition to being cost-effective, our previous experience with Nexans in terms of service, response time, as well as certifications is positively emphasised.”
Recommended Reading

EZO secures €150m debt facility for 3,000+ EV charge points
The financing will support more than 100MW of charging capacity across the UK and Ireland over the next three years.

ABB could have a big role to play in Rolls-Royce's SMR deployment
The exploratory MoU comes as site-specific design advances for the first three planned UK units at Wylfa.

National Grid to use flexible demand to manage voltage in 100 LV zones
National Grid DSO is preparing to use flexible electrical demand to help manage voltage constraints on the low-voltage network.