“Stands Scotland where it did?”
ScottishPower has been paid £107 million for switching off its wind turbines during a three-year delay in completing an undersea cable project which was supposed to solve that very problem.
ScottishPower has been paid £107 million for switching off its wind turbines during a three-year delay in completing an undersea cable project which was supposed to solve that very problem.
The £1 billion Western Link from Ayrshire to North Wales was specifically designed to prevent so-called “constraint payments”, by allowing more Scottish green electricity to reach consumers in England.
Previously, huge amounts of electricity from Scotland’s wind farms became stuck in a bottleneck at the Border, resulting in operators being paid millions of pounds to shut down – and the cost being passed on to household bills.
The new high voltage link, a joint venture between SP Energy Networks and National Grid, was commissioned in 2012 and the project was supposed to be completed by December 2015.
However, a series of major problems delayed that completion for well over two years. The Western Link then operated at a reduced capacity until last May – when it was shut down again – before finally coming online on 16 October.
So throughout that period, ScottishPower shareholders were being paid for doing almost entirely nothing. Shame that these shareholders are now to be found mostly in Spain. However much it wraps itself in tartan, the fact remains that it is Iberdrola of Madrid, not ScottishPower of Glasgow, that benefits.
The views and opinions expressed in this article are those of Kayleigh Hutchins and do not necessarily reflect the official policy or position of Electrical Review. This content represents individual perspective and industry commentary.
Recommended Reading

Are building operators owning their systems – or just renting access?
Who really controls a building once it is operational? Chris Timmins of IOTech Systems explores the growing case for open, edge-led systems.

Can automation help electrical contractors stop delays before they start?
Greg Edge, Managing Director at Edge Electrical Solutions, explores how structured data and automation can help contractors prevent costly delays.

Will commitment fees really solve the grid connection queue?
Equity Energies’ Elliott Meighan asks whether Ofgem’s new connection rules strike the right balance between readiness and financial strength.