SEGRO Park Rainham gains High Voltage connection
SEGRO Park, a business and industrial centre located just outside London in Rainham, Essex, has been connected to the High Voltage network.
SEGRO Park, a business and industrial centre located just outside London in Rainham, Essex, has been connected to the High Voltage network.
Worcestershire-based Independent Connections Provider (ICP), Rock Power Connections, finalised the installation of the High Voltage point of connection to the area.
Rock Power Connections was appointed to install Low Voltage mains from a new substation to HDCTs housed in GRP enclosure, on a client constructed plinth. The installation had already commenced when the company entered the fray; which added to the complexity of the install. Careful planning and logical perspective was essential to get switchgear delivered on site safely.
All previously installed cables were tested with fault-finding equipment. Defected cables were detected and repaired by Rock Power Connections before further works commenced. Despite this setback, Rock Power Connections completed all works before the meters were fitted.
Sophie Wells, project manager for Rock Power Connections, said, “This was a challenging install due to the existing LV network onsite, but by working closely with the developer and main contractor, we were able to compile a unique design which met both the IDNOs design standards and enabled each unit to be individually metered as per the developers requirement.
“The site was energised within the clients specified timescales and was a huge success, and it was great to be involved in such a pioneering development.”
SEGRO Park is an incredibly important industrial centre due to its commitment to sustainability. The buildings constructed on the site boast an EPC A+ rating, while the developer is targeting BREEAM ‘Excellent’ standards.
To achieve these sustainability goals, SEGRO Park boasts photovoltaic panels to all roofs and some walls, LED lighting and electric car charging points as standard. Further enhancements include the use of translucent wall panelling to increase natural daylight and the installation of a Tesla battery on Unit 8, to store generated electricity. All other units are ‘plug & play’ ready for the technology to be installed.
Recommended Reading

National Grid to use flexible demand to manage voltage in 100 LV zones

Can automation help electrical contractors stop delays before they start?
Greg Edge, Managing Director at Edge Electrical Solutions, explores how structured data and automation can help contractors prevent costly delays.

Aegis starts construction of multi-energy commercial vehicle charging hub
Aegis expects the site to open in spring 2027, with 72 van bays and 30 truck bays at full build.