National Grid completes erection of new T-pylons for Hinkley Connection Project
All 116 new T-pylons being constructed as part of National Grid’s Hinkley Connection Project have been erected.

All 116 new T-pylons being constructed as part of National Grid’s Hinkley Connection Project have been erected – a new milestone for the project.
The first T-pylons were constructed in March 2022, but now the project is almost complete thanks to the erection of the final T-pylons. These will carry low-carbon energy between Hinkley Point C to Seabank power station, providing electricity to six million homes and businesses in the South West of England.
The last of the T-structures’ 232 diamond-shaped insulators – which hold the high-voltage conductors in a diamond ‘earring’ shape – was recently lifted by crane into place on a T-pylon between Yatton and Kenn in North Somerset by National Grid and principal contractor Balfour Beatty.
T-pylons are quicker to erect than traditional lattice pylons, and 47 more T-pylons were completed – including installation of the conductors – by the end of 2022.
36 new T-pylons between Woolavington and Loxton were energised in early 2023, meaning high voltage electricity is now running along the new T-pylons, through cables under the Mendip Hills Area of Outstanding Natural Beauty and via the newly built substation at Sandford.
At the same time work began to build the 68 T-pylons running north of Sandford substation to Portbury. With the hanging of the final diamond insulator, those 68 T-pylon structures are now complete.
All the T-pylons will be energised by the end of 2024. Before then, conductors will be hung from the T-pylons, and the last of 249 traditional lattice pylons and 67km of overhead wires will be removed from the landscape to make way for the new electricity connection.
Roxane Fisher-Redel, Senior Project Manager for National Grid on the Hinkley Connection Project, commented, "National Grid’s T-pylons are the first new design for overhead electricity lines in over a century and will play a central role in connecting low-carbon energy to millions of people when Hinkley Point C begins generation.
"Erecting all the 116 T-pylon structures is a huge milestone and now we look ahead to 2025 and full completion of this project, which will play such a key role in transmitting cleaner, homegrown energy around the UK – enough to power six million homes and businesses."
The T-pylons were designed to reduce the visual impact of the 57km connection route on the landscape as a direct response to community feedback.
At 35m high, they are a third shorter than National Grid’s traditional lattice transmission pylons and take up less room on the land.
Recommended Reading

ADEPT calls for national action to close public EV charging gap
ADEPT says councils need long-term funding, clearer standards and fairer public EV charging to avoid leaving drivers without driveways behind.

National Grid clears key substation hurdle for next wave of Dogger Bank wind
National Grid has secured consent for Birkhill Wood substation, which will connect the next Dogger Bank offshore wind projects to the grid.

The all-new Electrical Review is here
Discover the all-new Electrical Review, built to deliver sharper news, deep dives and opinion on the UK’s electrification infrastructure sector today.
