CG powers E.ON’s Humber Gateway offshore wind farm
CG has been awarded the contract for the design, engineering, supply and installation of the onshore and offshore substations at the 219 MW Humber Gateway offshore wind farm in the UK.
CG has been awarded the contract for the design, engineering, supply and installation of the onshore and offshore substations at the 219 MW Humber Gateway offshore wind farm in the UK.
Humber Gateway is a Round 2 Offshore Wind Project owned by E.ON. The scheme is based on 73 multi megawatt turbines, power from which will be collected and delivered to the 280 MVA offshore substation platform. It will be transformed up to 132 kV and delivered onshore via 2 export cables to a new National Grid substation 30 km inland at Hedon on Staithes Road in Hull. CG’s scope in the multi-million pound contract includes detailed electrical system design with grid code compliance, supply of a high voltage Offshore Substation consisting of two step up power transformers, medium voltage and high voltage GIS installed by E.ON on a single jacket foundation and a 132/275 kV onshore substation works including two large autotransformers, reactive power compensation equipment, high voltage switchgear, an IEC 61850 based SCADA, protection and control, and civil works. The substations are scheduled to be installed and commissioned in 2013 and to become fully operational in early 2014.
CG was successful against established industry competition in securing this large reference project in the UK renewable sector. This win is said to demonstrate CG’s local project management strengths, expertise in working to National Grid requirements, onshore and offshore track record and cost-efficient approach in offering turnkey design and build grid infrastructure solutions that have been recognised by the client in awarding this strategic project to CG. “The UK will see 18 GW of offshore wind installed by 2020 and this first win provides CG a launchpad to secure a strong market share in this strategic sector and contribute to the UK’s 2020 green energy targets”, said Laurent Demortier, CEO and managing director of CG.
Recommended Reading

EZO secures €150m debt facility for 3,000+ EV charge points
The financing will support more than 100MW of charging capacity across the UK and Ireland over the next three years.

ABB could have a big role to play in Rolls-Royce's SMR deployment
The exploratory MoU comes as site-specific design advances for the first three planned UK units at Wylfa.

National Grid to use flexible demand to manage voltage in 100 LV zones
National Grid DSO is preparing to use flexible electrical demand to help manage voltage constraints on the low-voltage network.
