Wind in their sails
The first turbine at Scroby Sands, the offshore wind farm being developed by E.On UK, has started to generate electricity.
The turbine began turning on 19 July and will undergo a 10-day test period.
Once all 30 turbines have completed a test period, seeing them run for 240 hours continuously before E.On officially takes charge, they will be capable of producing enough electricity to supply around 41,000 homes.
The wind farm, located 2.5km from Great Yarmouth, should be complete by the end of August 2004.
Recommended Reading

Electrification alone won’t solve the heat challenge
Christophe Williams, founder of Naked Energy, asks whether we are putting too much of the heat challenge on the grid.

Could the Energy Independence Bill finally unblock the grid?
Planned changes to land access and installer registration aim to speed up grid upgrades while giving network operators a clearer picture of demand.

Europe's largest battery storage system goes live at Hams Hall
BW ESS says its 1,243MWh battery in North Warwickshire is now Europe's largest operational battery by energy storage capacity.