Areva’s Transmission and Distribution division has won a Euro20m contract with National Grid Transco (NGT), the UK’s largest transmission network owner and operator, to upgrade the electricity grid in central England.
The project will improve voltage stability and respond to increasing power demand in the West Midlands industrial region.
The first stage is to install two 400kV Mechanically Switched Capacitor Bank Damping Networks (MSCDN) in two locations to ensure voltage stability across the region. This is needed as a result of a changing generation market. The equipment boosts reactive power on the grid, thus stabilising the voltage. Areva T&D will design, install and commission MSCDNs at NGT’s Hams Hall and Drakelow substations.
The second stage is to extend NGT’s Feckenham 400/66kV main feeder substation to allow the local distribution network operator to satisfy the area’s rising consumer and industrial demand for energy.
For both solutions, Areva T&D will also provide the design, delivery and installation of all the digital protection and control systems required and undertake the civil construction works. The substation extension will be operational in March 2006 and the MSCDNs in October 2005.
Recommended Reading

EZO secures €150m debt facility for 3,000+ EV charge points
The financing will support more than 100MW of charging capacity across the UK and Ireland over the next three years.

ABB could have a big role to play in Rolls-Royce's SMR deployment
The exploratory MoU comes as site-specific design advances for the first three planned UK units at Wylfa.

National Grid to use flexible demand to manage voltage in 100 LV zones
National Grid DSO is preparing to use flexible electrical demand to help manage voltage constraints on the low-voltage network.