Preferred line route announced
Scottish and Southern Energy has announced its preferred route for a 400kV electricity transmission line, which must be built between the Highlands and the Central Belt of Scotland if the company is to meet government targets.
SSE says construction of the line and substations will cost around £200m. It hopes to begin work on the route in the first half of 2005, with the line operational by late 2007.
The 220km line will stretch from Beauly to Denny and will replace a 132kV line, which will be dismantled. Some 75% of the new line will run along the same route as the old one.
The chief executive of SSE, Ian Marchant, said: "The existing line was originally built to serve a very rural area with very low demand for electricity. It was not designed to cope with the large number of requests for connections to the electricity network that we are currently receiving from renewable energy developers.
"It is, therefore, vital that the wide support that exists for developing renewables in Scotland translates into a commitment to enabling this nationally-important infrastructure project to become a reality as soon as possible."
The route decision was reached after a 15-month study, in which SSE met with local authorities, statutory and non-statutory bodies and other interested parties. The company will enter another round of consultation on the proposed route and hopes to submit to the Scottish Executive in the third quarter of this year an application for consent to build the line.
Recommended Reading

ABB could have a big role to play in Rolls-Royce's SMR deployment
The exploratory MoU comes as site-specific design advances for the first three planned UK units at Wylfa.

National Grid to use flexible demand to manage voltage in 100 LV zones
National Grid DSO is preparing to use flexible electrical demand to help manage voltage constraints on the low-voltage network.

Aegis starts construction of multi-energy commercial vehicle charging hub
Aegis expects the site to open in spring 2027, with 72 van bays and 30 truck bays at full build.